Stimmel, Stimmel & Smith, P.C.


 

 

IMPACT AND ACCELERATION: THE HIDDEN CHANGE ORDER COST

 

 

Introduction:

 

When things go wrong, they go very wrong. That’s not just a pessimistic outlook: on a construction site, it is a fact of life and the reason is simple: work between the trades and within a particular trade are interrelated and a ripple in your own job schedule causes a ripple throughout the entire construction project affecting trades you might not even know are on the project in ways that might not be obvious to the novice in construction.

 

All of us are aware of the “Critical Path Programs” by which builders determine what trades come and go when, when materials are delivered, how the trades interact and, above all, when the owner may assume passing of inspections, use of the structure, and paying off the lender. Anyone who has seen such a program will quickly note that an alteration in one trade’s path directly affects all the trades sooner or later.

 

And what that means to anyone on a job site is that as good as you may be in doing your portion of the work, someone else’s error or bad luck can quickly make your own task not only delayed, but much harder and much more costly. Assuming you are an electrical contractor, your task is often subject to the plumbing contractor finishing their trenching. If you do dry wall, you are dependent on almost every other trade completing, etc, etc. As one client put it, “I have fifty other people making decisions on every job site that will decide if I make or lose money on the job.”

 

Does that make every job a complete gamble in which you have to hope that everyone does a decent job and has good luck or you face economic loss?

 

Not if you understand, account for, and contract for such possibilities in your construction documents. Not if you do your job in creating a contract that takes into account the effect of delays on the project, alterations in the Critical Path Program, and IMPACT AND ACCELERATION and how they affect your profitability.

 

The reader should first review several other useful articles related to this field on our web site. The articles on Mechanics Liens and Stop Notices,  Arbitration,  Contracts and, finally, Change Orders should all be read before proceeding below.

 

This article shall outline some of the basic issues each professional and owner on a construction project must consider in assessing the appropriate contract documents to fairly handle the common event of delays, whether intentional or not, on the project. No matter how good you are at your particular craft, if you do not create the right contract documents, you face significant loss on every project absent close adherence to some basic approaches described below.

 

 

1. Scheduling on the Job Site

 

A chef once told the author that the secret of making a good breakfast is timing. “You have to have the bacon begun before the eggs, but all coming out the same time along with hot toast and butter. Mess that up, and you have cold eggs, burnt toast and rubbery bacon. You get fired.”

 

Timing is how general contractors earn their living. Their “meal” is a construction project with often two dozen trades, an architect, engineer, lender and owner all looking over their shoulder, with such matters as weather, illness, unions and material suppliers all having a hand in the schedule created.

 

It is thus no wonder that volumes of books and dozens of computer programs have been created to allow them to create flexible and effective critical path and related programs to develop appropriate  methods to handle the common problem of delays and changes in the job path. Such methods include Bar Charts, Critical Path Programs, “LJ” Methods, Precedence Diagramming Methods, Progress Curves, Production Curves, and a host of other concepts and plans.

 

From the professional and legal point of view the issue comes down to whether the effects of delay will be compensated and adjusted for or will certain persons on the site have to “stomach” the results without compensation. That usually comes down to two factors: whether such effects are truly recognized and understood by the people on the site; and what contract terms and the law requires if such effects are recognized.

 

What do we mean by “recognized?”  Many changes do NOT have much effect on the job. Installing conduit in one building or another first often does not require much more than asking your workers to set up a hundred feet from where they were planning in any event. Altering the order of installation often makes no difference to certain trades at certain times.

 

But other delays can be catastrophic. A trade which must finish before you can start suddenly files bankruptcy and is delayed for three months; another trade failed to order materials and you cannot put on dry wall since no conduit is in the wall; the engineer fails to provide accurate or timely plans and thus the specifications have to be altered mid way through installation: the variations are endless and the impact can be significant for the job and the various contractors.

 

And then the typical argument begins. Owner and General argue that the change is “neutral” in terms of economic loss and that it is a simple and unimportant alteration in minor scheduling. The subcontractors or material men argue that it is catastrophic, will triple their cost to do the job and disrupts their schedule not only on the project but on the next three projects they are contracted to perform, etc, etc.

 

Unless you have contracted such relief away (and at times, even if you did) it is possible, especially in arbitration, to get fair compensation for the effects of delay and alterations in the schedule not caused by your own negligence. Ideally, the scope of such additional compensation will be spelt out in detail in the contract. If not, equitable principals may apply with “fair and appropriate” compensation being awarded.

 

2.  Impact and Acceleration

 

The two theories of impact and acceleration simply describe two of the effects of changes of scheduling on a job site. Impact describes how the change can cause damage due to alterations in labor costs, equipment costs, material costs, bonding costs, subcontractor costs, overhead costs and effect on other projects. (For example, the need to use overtime to make up for delays; the need to extend a bond or hold materials and store same, etc. etc.) Acceleration relates to the lost productivity one encounters when one is forced to utilize overtime and shuffle workers in and out in a desperate effort to finish a job on time when others have caused a delay in the start or a cessation in work.

 

Many studies have scientifically analyzed the effect of longer hours, stress and overtime on productivity of personnel. There are precise graphs indicating how the per hour out put of an individual worker declines as overtime is increased and when one is facing overtime of weeks or more, the productivity can decline to truly significant levels. Additionally, errors on the job, accidents, and relationship between management and employees can be strained due to the long term effect of continued increased hours.

 

The damages are far from illusory and even the increased rate for overtime seldom fully compensates management and employees for the overall effect of the need to increase performance. The writer well remembers one client who lost his best foreman due to the pressure of one seemingly endless period of overtime since the heated exchanges of that over charged atmosphere led to recriminations and ill feeling that made further working together nearly impossible. The owner of the company sadly commented that no increased compensation could have made him whole after that horrendous disruption.

 

Other companies almost thrive on the high pressure atmosphere of a job that has been accelerated in time performance due to events on the site-so long as they are adequately compensated for it, of course. Indeed, some companies bid government jobs precisely because they anticipate massive change orders which will form the bulk of their profits from the project.

 

As discussed in the appropriate section below, the key is to both anticipate and provide appropriate fair compensation that takes into account not only the increased hours needed for the change order or other alteration in performance required, but the long term effect of impact and acceleration

 

Most direct costs are easy to quantify. Increased bonding costs, material man penalties or shipping cost increases, etc, etc. can usually be verified. It is the indirect costs…the increase in absenteeism, lack of productivity, disruption of other jobs, that is harder to demonstrate especially when one seeks to place a monetary amount on the damages caused. For example, in order to complete an accelerated job on time, one client assigned his best people to a particular job, performed as required and earned good extra compensation for the task. However, the other projects his company was working on all suffered and he later advised the writer that a subsequent piece of litigation for breach of warranty of good workmanship on another project stemmed directly from his assignment of his best people to a different job. How does one factor that element of cost into one’s project or claim for damages?

 

In short, the effects of acceleration are not only immediate in resulting lost of productivity and quality of work, but long term in the effects on other projects, labor and management relationships, reputation in the field, etc.

 

 

4. Contractual and Other Protections

 

As discussed in other articles on this site (See Change Orders) alterations on jobs are common in the industry and most construction agreements have long provisions relating to how change orders are to be handled. Most such clauses are designed to give some protection to the parties and to allow some type of additional compensation to the builder who faces change orders that increase duties on the project. (As stated in the other article, the builder would do well to carefully read the standard provisions which are often one sided and designed NOT to provide true compensation for such alterations: proper attention to correct clauses is needed by all parties.)

 

Many contracts and, indeed, many owners do not fully account for the true impact and acceleration effects on the job site, assuming that some increase in overtime or general compensation on the project will suffice. What they fail to understand is the proven cumulative effect of increased requirements of performance and speed of performance in terms of lost productivity.

 

Typical contractual change order risk shifting provisions involve granting the owner the right to suspend work for limited periods of time; allow shifts in scheduling; provide no damages for delay and provide no damages for alterations beyond the control of the owner. Very few contractual provisions allow compensation for impact and acceleration.

 

Luckily, in California and many other states, the law implies duties in all contracts, including construction agreements, and such relief as mechanics liens and stop notice claims, which are equitable, can allow arguments for damages which allow such types of claims.

 

The implied duties include:

 

a. Duty not to hinder, delay or interfere with contractor’s performance.

b. Duty to cooperate

c. Duty to act in good faith and to demonstrate fair dealing;

d. Duty to provide Site Access

e. Duty to Review Submittals in a timely manner.

 

Especially in such a forum as arbitration, with construction professionals often acting as triers of fact, equitable principles can overcome even contrary contractual protections and this writer has seen arbitrators impose the general California law of allowing impact and acceleration damages even when the contract seemed to mitigate against such damages.

 

It is vital to have a good contract with fair provisions, but relief may be available if a good case of equitable entitlement to relief can be demonstrated. Typically, if the owner acted in a manner to make efficient running of your part of the project possible, and this caused significant delay and impact, one can normally seek relief.

 

5. Burdens of Proof

 

Whether or not based on contract, the person claiming damages has the burden of proof to establish the amount and rationale for the damages. See our article on Contracts. This necessarily includes damages predicated on impact and acceleration. Essentially, the claimant must demonstrate that the need for increased performance was not predicated on factors created by the claimant’s own negligence or breach of contract or by factors beyond the control of the owner or general contractor.

 

Typical factors that are beyond the control of the owner include “Acts of God” which are usually defined by the Courts or arbitrators as disasters such as earthquakes, fire, weather, tsunamis, etc. Acts of terrorism, labor strikes beyond the control of owner, governmental acts, etc. are also considered beyond the control of the other party. Often the trier of fact will grant extra days for the claimant to perform if such acts occur, but not grant damages against the other party who, after all, did not breach the contract.

 

If seeking compensation, the claimant has the continuing duty to demonstrate by a preponderance of the evidence that the other party caused the events which constituted the need for acceleration and impacted performance and that said causes were either negligent, violated the implied duties, or were a breach of contract. Then the claimant must also demonstrate the actual damages incurred, often using experts with the various graphs and studies to demonstrate the extent of the acceleration damages.

 

Clearly adequate and complete record keeping is vital for any party in any such proceeding, demonstrating with as much precision as possible the extent of the disruption and the degree of extra costs incurred. Legal advice is vital to determine what damages may lie: for instance, certain indirect costs such as set overhead (Home Office overhead) is often rejected for the simple reason that such overhead was not impacted by the alleged breach. A good law office can specify in detail what damages may apply in a particular situation.

 

And recall that the owner or general contractor may have powerful counter arguments to advance and usually do not have the burden of proof. Assuming the claimant’s own delay contributed to the overall delay of the entire job, the trier of fact will be faced with the need to allocate responsibility and, if in doubt, will find against the claimant who, after all, has the burden of proof.

 

 

6. Types of Inefficiency Damages

 

It is clear from the above analysis that a good deal of the damages sought in such cases involved the increased inefficiency caused to the claimant by the various alterations in the project. It is necessary for the claimant to demonstrate that not only does such inefficiency occur frequently when acceleration of a project occurs but that it actually occurred in the particular case. This necessarily requires attention (and proof) that some combination of the following factors caused measurable loss on the job. This list is far from exhaustive: it merely gives a sample of the types of damages that may be proven and some combination of these must be proven or no damages will lie.

 

1. Out of Sequence Work

 

2. Crowding and Stacking of Trades Causing Disruption.

 

3. Overtime was required with the resultant increase in cost and decrease in efficiency of the worker

 

4. Restricted Site Access may have occurred not only on the site but in public transport to the site due to timing of work

 

5. Inefficiency may also have been caused by manpower shortages, e.g. there simply were not sufficient people to do the work efficiently regardless of the offer of over time.

 

6. Disruption of office planning and material deliveries; extra costs for materials

 

7. Need to provide additional security on the job site for both materials and personnel

 

8. Need to compensate in some manner other customers due to delay and disruption to their needs.

 

 

Proof of the above damages is normally accomplished by expert witnesses who have made studies of quantification of the results of impact and acceleration and whose testimony is usually found convincing by triers of fact. However, to make their testimony credible requires accurate and complete records being kept by the claimant, and effective cross examination of such witnesses will usually focus on whether the claimant can sufficiently demonstrate cause and effect and the actual results of the changes on the job.

 

 

7. The Contract Terms

 

As discussed in other articles on this Web Site, the typical construction contract seeks to limit or waive such claims by complex change order requirements or, more simply, blanket waivers of any right to these damages. These provisions must be carefully considered before executing the contracts and if the contract is already executed, carefully analyzed to determine if the equitable principles available in most construction disputes and arbitration can surmount the limitations inherent.

 

Quite often one discovers that the trier of fact will find some way to “do what is right and fair” and one encounters the odd fact that some clauses, which are so extreme as to be absolutely unfair, so annoy the arbitrator that they are simply ignored. Our office has found that balanced and fair provisions have a far better chance of being effective and enforceable than the almost vicious provisions so beloved of attorneys who have never had to actually try such a case. Fairness, not unadorned power, is the hall mark of a good construction agreement but the person signing a contract or seeking to enforce it must be aware that some courts do enforce strict waiver provisions and it is vital to have good legal counsel review the contract before assuming its obligations. If you have already signed such a contract and face repercussions much more extreme than you first imagined, do not immediately assume there is no relief. Keep in mind that equitable considerations may allow relief and such relief may include the impact and acceleration damages described above.

 

 

Conclusion:

 

It is true that one of the skills in becoming a construction professional is learning to juggle the numerous and varied elements in a construction project and “roll with the punches” that occur in even the best construction project.

 

Nevertheless, the simple fact is that the effect of someone’s breach of their obligations and the resultant change order is not the simple immediate increased direct costs on the job but more subtle but still important medium and long terms costs. It is vital for anyone in construction to recognize that simple fact, integrate it into construction documents and contracts, and plan for the same when a job must be speeded up…to finish on time.

These Articles are to give the reader a general description of certain areas of the law. Legal advice is necessary to apply these legal concepts to your particular situation. The Reader should obtain competent legal advice before relying on the Articles.

Return to Articles Index Page

 

HomeFirm ProfileAttorneysArticlesNewsletterRetainer Area


© Copyright 2004 Stimmel, Stimmel & Smith, P.C. All Rights Protected.